Client
Yarra Valley Water
Site
Park Orchards, Victoria
Installed
2021-22
Melbourne Pipelines Team
Leigh Sinclair
Shem Macdonald
Glenn Thompson
Rob Razzi
Steve Avramovski
John Williamson
Purpose:
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their Community Sewerage Program by 2035.
What we accomplished:
The scope of this project that MPL completed for Yarra Valley Water was:
Construction of a gravity and pressure sewerage reticulation system for approximately 64 properties.
451m of PE pressure sewers up to DN63 in size and 775m of PVC gravity sewer DN150 in size.
8 maintenance holes, 5 maintenance shafts, 2 inspection shafts.
1 isolation valve, 1 flushing points, 1 air valve and green odour dome filter.
Gravity property connections including 23 non live sewer and 11 live sewer conditions (includes road crossing and non-road crossing connections).
Pressure property connections including 18 non live sewer and 12 live sewer conditions (includes road crossing and non-road crossing connections).
Multiple live sewer works and live sewer maintenance hole modifications and lining.