Client
Yarra Valley Water
Site
North Warrandyte, Victoria
Installed
2013-2015
Melbourne Pipelines Team
Leigh Sinclair
Shem Macdonald
Rob Razzi
Glenn Thompson
Steve Tsotsos
Steve Avramovski
Purpose:
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their sewerage backlog program by 2025.
What we accomplished:
The scope of this project that MPL completed for Yarra Valley Water was:
Construction of a hybrid sewerage reticulation system for approximately 346 properties.
5.2km of PE pressure sewers up to DN75 in size.
5.1km of PVC/PE gravity sewers up to DN225 in size and up to 8.0m deep.
92 maintenance structures (up to more than 8.0m deep)
A number of flushing/scour points, isolation and air valves
A number of road crossings and property connections