Client
Yarra Valley Water
Site
Olinda, Victoria
Installed
2024-25
Purpose:
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their Community Sewerage Program by 2035.
Melbourne Pipelines Team
Leigh Sinclair
Shem Macdonald
Alec Wood
Glenn Thompson
Rob Razzi
Steve Avramovski
John Williamson
What we accomplished:
The scope of this project that MPL completed for Yarra Valley Water was:
Construction of a pressure sewerage reticulation system for approximately 147 properties.
4.7km of PE pressure sewers DN50 up to DN125 in size.
20 isolation valves, 15 flushing points, 4 non-return valves, 5 air valves and green odour dome filter.
147 pressure property connections (including road crossing and non-road crossing connections).