Client
Yarra Valley Water
Site
Monbulk, Victoria
Installed
2021-23
Melbourne Pipelines Team
Leigh Sinclair
Shem Macdonald
Glenn Thompson
Rob Razzi
John Torre
John Williamson
Purpose:
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their Community Sewerage Program by 2035.
What we accomplished:
The scope of this project that MPL completed for Yarra Valley Water was:
Construction of a pressure sewerage reticulation system for approximately 237 properties.
6.2km of PE pressure sewers up to DN90 in size and 2.1km of PE rising mains DN125 in size.
46 isolation valves, 42 flushing points, 1 air valve and green odour dome filter.
37 road crossing and 200 non road crossing property connections.
Booster Pump Station (mechanical, civil, structural and electrical works).