Client
Yarra Valley Water
Site
Donvale, Victoria
Installed
2019-20
Melbourne Pipelines Team
Leigh Sinclair
Shem Macdonald
Rob Razzi
Glenn Thompson
John Torre
John Williamson
Purpose:
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their sewerage backlog program by 2035.
What we accomplished:
The scope of this project that MPL completed for Yarra Valley Water was:
Construction of a hybrid sewerage reticulation system for approximately 185 properties.
1.2km of PE pressure sewers up to DN63 in size.
5.4km of PVC/PE gravity sewers up to DN225 in size and up to 9.0m deep.
71 maintenance structures (up to more than 9.0m deep).
8 flushing/scour points.
10 isolation and air valves.
Several road crossings and property connections.
Decommission SPS094 and 095.