Client
Yarra Valley Water
Site
Kallista & The Patch, Victoria
Installed
2022-23
Melbourne Pipelines Team
Leigh Sinclair
Shem Macdonald
Alec Wood
Glenn Thompson
Rob Razzi
Steve Avramovski
John Williamson
Purpose:
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their Community Sewerage Program by 2035.
What we accomplished:
The scope of this project that MPL completed for Yarra Valley Water was:
Construction of a pressure sewerage reticulation system for approximately 318 properties.
8.6km of PE pressure sewers up to DN90 in size.
33 isolation valves, 27 flushing points, 4 air valves and green odour dome filters.
263 pressure property connections.
55 pressure property connections into existing PE transfer main.
Booster Pump Station (mechanical, civil, structural and electrical works).