Warrandyte Backlog Sewerage Scheme – Package One
Purpose
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water have developed a strategic objective of completing their sewerage backlog program by 2025.
What we accomplished
The scope of this project that MPL completed for Yarra Valley Water was:
- Construction of a hybrid sewerage reticulation system for approximately 285 properties.
- 8.2km of PE pressure sewers up to DN63 in size.
- 5.7km of PVC/PE gravity sewers (up to DN150 in size and 5m deep).
- 100 maintenance structures.
- Flushing/scour points, isolation and air valves.
- Road crossings and property connections.
- Live sewer works.
Client
Yarra Valley Water
Site
Warrandyte, Victoria
Installed
2012-
2014
Team
Lou Razzi
Leigh Sinclair
Shem Macdonald
Rob Razzi
Glenn Thompson
Steve Tsotsos
Melbourne Pipelines approached the job very professionally. We wish we could deal as easily with all people that come onto our property. They certainly helped inspire confidence.
Donvale Customer