Monbulk Community Sewerage Project – Package C

Purpose

There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their Community Sewerage Program by 2035.

What we accomplished

The scope of this project that MPL completed for Yarra Valley Water was:

  • Construction of a pressure sewerage reticulation system for approximately 237 properties.
  • 6.2km of PE pressure sewers up to DN90 in size and 2.1km of PE rising mains DN125 in size.
  • 46 isolation valves, 42 flushing points, 1 air valve and green odour dome filter.
  • 37 road crossing and 200 non road crossing property connections.
  • Booster Pump Station (mechanical, civil, structural and electrical works).
Client
Yarra Valley Water
Site
Monbulk, Victoria
Installed
2021-
2023
Team
Leigh Sinclair
Shem Macdonald
Glenn Thompson
Rob Razzi
John Torre
John Williamson
Melbourne Pipelines demonstrates exceptional partnership and industry leading expertise. It was a pleasure to spend over 5 years working closely with Melbourne Pipelines to deliver Yarra Valley Water’s Community Sewerage Program. At all times asset quality, safety and exemplary customer service were a priority for Melbourne Pipelines. Leigh and his team have a culture of continuous improvement, always transferring learnings from one project to the next, and working with the client to improve overall the overall delivery process and design quality. Melbourne Pipelines routinely adopt an early engagement approach to identify and address risks before they can be realised and collaboratively solve problems with all relevant stakeholders jointly.
Sally Crook
Community Sewerage Program Team Leader Yarra Valley Water