Olinda-Menzies Creek Upper Transfer Main

Purpose

There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their sewerage backlog program by 2035.

What we accomplished

The scope of this project that MPL completed for Yarra Valley Water was:

  • Construction of a transfer rising main (4.1km of DN160 PE sewer).
  • A number of flushing/scour points.
  • A number of isolation and air valves.
  • A number of road crossings.
Client
Yarra Valley Water
Site
Kallista, Victoria
Installed
2019
Team
Leigh Sinclair
Shem Macdonald
Glenn Thompson
Rob Razzi
Steve Avramovski
John Torre
John Williamson