Donvale Backlog Sewerage Scheme
Purpose
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their sewerage backlog program by 2025.
What we accomplished
The scope of this project that MPL completed for Yarra Valley Water was:
- Construction of a hybrid sewerage reticulation system for approximately 67 properties.
- 1.6km of DN40 to DN160 PE pressure and gravity sewers.
- A number of maintenance structures.
- A number of flushing/scour points, isolation and air valves.
- A number of road crossings and property connections.
- Live sewer works.
Client
Yarra Valley Water
Site
Donvale, Victoria
Installed
2009
Team
Leigh Sinclair
Glenn Thompson
Lou Razzi
Despite the challenges which may have occurred along the way, it was your professionalism and work ethic which made the journey a pleasant one. The way your team go about their work in the field is reflected by the very limited number of issues which ever get brought to our attention. This tells me you’ve got yourself a team who take pride in their work and do a good job of it too.
Dean Anderson
Donvale Project Manager Yarra Valley Water