Donvale Backlog Reticulation – Package E
Purpose
There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their sewerage backlog program by 2025.
What we accomplished
The scope of this project that MPL completed for Yarra Valley Water was:
- Construction of a hybrid sewerage reticulation system for approximately 290 properties.
- 2.6km of PE pressure sewers up to DN63 in size.
- 8.4km of PVC/PE gravity sewers (up to DN315 in size and 10m deep).
- 121 maintenance structures (up to 10m deep).
- A number of flushing/scour points, isolation and air valves.
- A number of road crossings and property connections.
Client
Yarra Valley Water
Site
Donvale, Victoria
Installed
2017-
2019
Team
Leigh Sinclair
Shem Macdonald
Rob Razzi
Glenn Thompson
John Torre
John Williamson
Steve Tsotsos
Steve Avramovski
Melbourne Pipelines approached the job very professionally. We wish we could deal as easily with all people that come onto our property. They certainly helped inspire confidence.
Donvale Customer

I would consider Melbourne Pipelines to be a contractor that looks after our interests and is responsive to our needs. It provides excellent customer services and often suggests improvements to our designs. It has implemented good quality, environmental and safety management plans. Melbourne Pipelines are definitely a dependable and reliable partner in the delivery of quality assets to service our customers.
Mon Gan
Team Manager Sewerage Growth Projects Yarra Valley Water