Purpose

There are a number of suburbs located within Yarra Valley Water’s supply area requiring reticulated sewerage services. These areas constitute Yarra Valley Water’s sewerage backlog program. In response Yarra Valley Water has developed a strategic objective of completing their Community Sewerage Program by 2035.

What we accomplished

The scope of this project that MPL completed for Yarra Valley Water was:

  • Construction of a gravity and pressure sewerage reticulation system for approximately 64 properties.
  • 451m of PE pressure sewers up to DN63 in size and 775m of PVC gravity sewer DN150 in size.
  • 8 maintenance holes, 5 maintenance shafts, 2 inspection shafts.
  • 1 isolation valve, 1 flushing points, 1 air valve and green odour dome filter.
  • Gravity property connections including 23 non live sewer and 11 live sewer conditions (includes road crossing and non-road crossing connections).
  • Pressure property connections including 18 non live sewer and 12 live sewer conditions (includes road crossing and non-road crossing connections).
  • Multiple live sewer works and live sewer maintenance hole modifications and lining.
Client
Yarra Valley Water
Site
Park Orchards, Victoria
Installed
2021-
2022
Team
Leigh Sinclair
Shem Macdonald
Glenn Thompson
Rob Razzi
Steve Avramovski
John Williamson
Melbourne Pipelines demonstrates exceptional partnership and industry leading expertise. It was a pleasure to spend over 5 years working closely with Melbourne Pipelines to deliver Yarra Valley Water’s Community Sewerage Program. At all times asset quality, safety and exemplary customer service were a priority for Melbourne Pipelines. Leigh and his team have a culture of continuous improvement, always transferring learnings from one project to the next, and working with the client to improve overall the overall delivery process and design quality. Melbourne Pipelines routinely adopt an early engagement approach to identify and address risks before they can be realised and collaboratively solve problems with all relevant stakeholders jointly.